Photo Gallery
Jump To Bottom
Feb. 28, 2007
Jan. 31, 2007
Dec. 20, 2006 (and Jan 3, '07)
Nov. 30, 2006
Oct. 31, 2006
Sept. 28, 2006
Aug 30, 2006
July 27, 2006
Feb. 28, 2006
Feb. 2, 2006
Jan. 3, 2006
Nov. 29, 2005
June 22, 2005
Sept.29, 2004 - First Construction (demolition only) Progress
September 5, 2002
September 19, 2002
October 17, 2002
November 7, 2002
November 21, 2002
Feb. 28, 2007 Progress Photos
-
Feb. 28, 2007
(pdf page) Only Photo:
Phase 1 Work is complete: This is a view looking easterly at the newly planted trees along Ashley Station Boulevard Park.
Jan 31, 2007 Progress Photos
-
Jan 31, 2007
(pdf compilation) Photos include:
E Wynnton Phase 1 Area – 9 Home Program south side of 8th Street – Buildings 1, 2, 3 and 4
E Wynnton Phase 1– 9 Home Program south side of 8th Street – Buildings 7, 8, 9
Peabody Site - view looking northerly along Midland Ave, Talbotton Road in the foreground. Building 7 at left side nearest.
Ashley Station Phase 1 Development – new management office on the new Olive Street
Ashley Station Phase 1 Development – view looking easterly along the new Olive Street with the New Leasing Office at left side.
view looking easterly along the new Ashley Station Boulevard Park.
Ashley Station Phase 1 Development Area – Building 19 at left, Building 9 in far background and Building 10. Poolside gazebo at right side
Dec 20, 2006 and Jan 3, 2007 Progress Photos
-
Dec. 20, 2006 and Jan 3, 2007
(pdf compilation) Photos include:
E Wynnton Phase 1 Area – 9 Home Program south side of 8th St - Buildings 1, 2, 3
E Wynnton Phase 1– 9 Home Program south side of 8th Street – Buildings 7, 8, 9
Peabody Site - view along the new 24th Street looking easterly from North Avenue.
Building 14 at left side; Buildings 13, 12, 6 and 11 at right side.
Ashley Station Phase 1 Development – Building 14 at corner of North Avenue and new 24th Street
Ashley Station Phase 1 Development – New Lease Office; Building 21.
Ashley Station Phase 1 Development Area – Building 11.
Ashley Station Phase 1 Development Area – Building 10.
Ashley Station Phase 1 Development Area – Building 4.
Nov. 30, 2006 Progress Photos
-
Nov. 30, 2006
(pdf compilation) Photos include:
E Wynnton Phase 1 Area – 9 Home Program south side of 8th Street – Buildings 6, 7, 8, 9
E Wynnton Phase 1– 9 Home Program south side of 8th Street – Buildings 1, 2, 3, 4
Peabody Site - view along the new Ashley Station Boulevard looking east from 10th Avenue across the new Boulevard Park Area
View looking westerly along new Olive Street. Building 10 at left; Building 11 beyond. Landscaping in process.
Building 5 nearing construction completion.
View looking westerly along the new 24th Street toward North Avenue; Buildings 12 and 13 at left, nearing construction completion.
Oct. 31, 2006 Progress Photos
-
Oct. 31, 2006
(pdf compilation) Photos include:
E Wynnton Phase 1 Area – 9 Home Program south side of 8th Street – Buildings 7, 8, 9
E Wynnton Phase 1– 9 Home Program south side of 8th Street – Buildings 1, 2, 3, 4, 5
view along the new Ashley Station Boulevard looking easterly – Buildings 16 and 15 at left and Building 3 in background
Ashley Station Phase 1 Development – view looking northerly along new 11th Street from Talbotton Road. Building 8 at right; Buildings 9 and 10 at left; Management Office in background
Buildings 12 and 13 under construction. Building 6 (3 story at end) nearing completion.
Ashley Station Phase 2 Development Area – Boulevard ready for new paving October 31.
Sept. 28, 2006 Progress Photos
-
Sept. 28, 2006
(pdf compilation) Photos include:
E Wynnton Phase 1– 9 Home Program south side of 8th Street – Buildings 1, 2, 3, 4 under construction.
View along the new Olive Street from the traffic circle. Getting ready to complete paving. Building 19 at left with Building 10 and 11 beyond
View along the new Midland Street looking toward Talbotton Road from the traffic circle. Ready for final paving to complete connection to Talbotton Road.
view of the green space around Buildings 1 and 3 (Building 3 at left)
Management Office - view from traffic circle – swimming pool under construction in front of the building.
Aug. 30, 2006 Progress Photos
-
Aug. 30, 2006
(pdf compilation) Photos include:
E Wynnton – foundations under construction at Lots 1 through 5; south of 8th Street.
View into site from Talbotton Road along the new 11th Avenue.
View along 27th Street. Building 17 and 18.
View into the site along the new 24th Street from existing North Avenue.
View westerly along Midland Park Boulevard toward the Phase 2 Development Area. Infrastructure in progress.
July 27, 2006 Progress Photos
Feb. 28, 2006 - March 1, 2006 Progress Photos
-
Feb. 28, 2006
Pictures include:
02-28-06 view looking northwesterly across the work area from Ivy Avenue.
02-22-06 view looking northerly across the site from Ivy Avenue. Buildings 7 and 8 under
construction.
02-28-06 view of new building construction. Building 16 in construction. View from south
side, the new Midland Boulevard.
02-28-06 difficult soil conditions at area of new traffic circle, intersection of Peabody Ave
and Midland Boulevard. Georgia Power in process of installing temporary power services.
Buildings 7, 8 and 19 in background.
03-01-06 Infrastructure Construction at the East Wynnton Site, north side of 8th Street
03-01-06 Infrastructure Construction at the East Wynnton Site, south side of 8th Street.
Clearing and grubbing in the area of the new detention pond
Feb. 2, 2006 Progress Photos
-
Feb. 2, 2006
Pictures include:
View looking northwesterly across the work area from Ivy Avenue. The new 11th
Avenue from Talbotton Road in the foreground.
View looking northerly across the site. The new 11th Avenue in the foreground, Buildings
15, 16, 17 and 18 in construction in the background.
view of new building construction. Looking westerly along 27th Street at Building #1 from
the east. Georgia Power at right side making revisions to existing overhead power services on
27th Street.
Jan. 3, 2006 Progress Photos
-
January 3, 2006
Pictures include:
View looking northwesterly across the work area
from Ivy Avenue. The new 11th Avenue from Talbotton Road under
construction.
View looking southerly
across the site. The new Midland Boulevard Park in construction,
illustrating typical site conditions following wet weather
View of new building construction. Below slab
piping installed; preparing for installation of granular and concrete
pour at foundation-floor slab.
Nov. 29, 2005 Progress Photos
-
November 29, 2005
Pictures include:
View looking northerly across the work area from Ivy Avenue
View looking northeasterly across the site from existing 26th
Street dead end
June 22, 2005 Cleared Site Progress Photos
View of Phase 1 and Phase 3 site areas (cleared)
September 29, 2004 First Construction (Demolition Only) Progress Photos
View along Talbotton Road
View East from Ivy Ave
View of 27th St. from Intersection of Talbotton and 27th
September 5, 2002 Resident HOPE VI Training Session
|
Left click on a thumbnail image below to see the full photo.
|
|
|
|
|
|
|
|
|
September 19, 2002 Resident Meeting #1
|
Left click on a thumbnail image below to see the full photo.
|
|
|
|
|
|
|
|
|
|
|
|
|
October 17, 2002 Resident Meeting #3
|
Left click on a thumbnail image below to see the full photo.
|
|
|
|
|
|
|
|
|
|
|
|
|
November 7, 2002 Resident Meeting #4
|
Left click on a thumbnail image below to see the full photo.
|
|
|
|
|
November 21, 2002 Resident Meeting #5
|
Left click on a thumbnail image below to see the full photo.
|
|
|
|
|
|
|
|
|
Jump To Top
Copyright © 2002 Boulevard Group, Inc.
484 Boulevard, SE
Atlanta, GA 30312
Main: (404) 622-7879
Support: (678) 428-8635 (Anytime Night or Day)
E-mail: Support
Release: 1.002.004  Release Date: October 15, 2004 ID: 489815504
|